30 April, 2024

Phase 1 of the adapted irrigation network in Fuentes de Ebro has been tested.

The first phase of the new pipeline for the irrigation system of the Huerta del Ebro Irrigation Community, in Fuentes de Ebro, Zaragoza, has been completed, reaching 1,350 meters of this infrastructure. During the last week of April, a test run of the installation was carried out, with satisfactory results, and it could be used by its users immediately.
30 January, 2024

Provisional irrigation systems enabled during the work to adapt the Ebro Orchard Community system to floods

The scarcity of winter rains has allowed progress to be made on the work, but unfortunately it is detrimental to crops. For this reason, temporary irrigation has been set up in the fields surrounding the works to save crops, in agreement with the irrigation community and in keeping with the Project's spirit of participation and cooperation.